MyReporter: What's the latest on the Hampstead Bypass?

A groundbreaking ceremony was held in 2022 for the first leg of the Hampstead bypass. The multi-section project is expected to cost around $429 million and is scheduled to be completed by 2030.
A groundbreaking ceremony was held in 2022 for the first leg of the Hampstead bypass. The multi-section project is expected to cost around $429 million and is scheduled to be completed by 2030.

Looking to ease traffic and improve safety around the U.S. 17 corridor in Pender and New Hanover counties, the Hampstead Bypass will provide a route around Scotts Hill and Hampstead by the end of the decade.

The estimated $429 million project is split in two segments. Work on Segment B, which extends from N.C. 210 to north of Hampstead, began in March 2022 and is currently under construction.

Segment A extends from N.C. 140, formerly known as the U.S. 17 Wilmington Bypass, to N.C. 210. The two segments together will stretch 13 miles in total.

A map showing the planned Hampstead bypass.
A map showing the planned Hampstead bypass.

Bypassing busy Hampstead looks to improve traffic and safety along U.S. 17, as well as ease traffic congestion in the Pender County community.

When will each segment open?

Construction on Segment B is scheduled to open to traffic by 2026. Originally, construction on Segment A was set to break ground in the fall of 2026, but officials with the N.C. Department of Transportation and the Wilmington Metropolitan Planning Organization announced in late 2022 an agreement to expedite that timeline. Now, it is estimated work on Segment A will break ground in summer 2025.

The project has been in the works for over a decade. In 2011, the initial environmental impact statement was approved and the first public hearing was held. Right-of-way acquisition began in 2018 for both sections of the Hampstead Bypass, and construction began in early 2022.

Traffic travels along the Military Cutoff Road extension Thursday Sept. 28, 2023 in Wilmington, N.C. After five years the extension, which cost $106 million − not including property acquisition costs − will be open. Nearly 60,000 drivers a day that use that area along Market between Gordon and Middle Sound Loop roads will be looking forward to the change. KEN BLEVINS/STARNEWS

When will the project be completed?

The entire bypass is expected to be complete and open to traffic by 2030. Both segments are being funded through the NCDOT’s State Transportation Improvement Program.

The project will link up with the recently completed Military Cutoff Road extension, a four-mile extension which was under construction in northern New Hanover County for five years and officially opened to traffic in September.

Do you have a question about the Wilmington area that you'd like a StarNews journalist to try to answer? Send an email to [email protected].

This article originally appeared on Wilmington StarNews: What's the latest on the Hampstead Bypass?